SHYAM SEL LTD.
JHARKHAND |
|
|
|
1 MTPA Integrated
Steel Plant at
Sinni |
|
|
|
Facilities |
|
Pig
Iron |
0.25
MPTA |
|
Sponge
Iron |
0.64
MPTA |
|
SMS |
0.45
MPTA |
|
TMT |
0.45
MPTA |
|
Coal
Washery |
3.6
MPTA |
|
Power
Plant |
150
MW |
|
|
| |
|
Current Status : |
|
|
|
1.
MOU to be signed with
Jharkhand Govt. Shortly
2.
Land already acquired
3.
All important plants and
Machineries ordered
4.
EMA under process
5.
Civil work already
started
6.
Feasibility study for
Railway siding
completed. DPR under
preparation |
| |
|
Shyam Metallics Ltd.,
Jamuria, West Bengal |
| |
|
Proposed Manufacturing
Facilities : |
| |
| |
Phase I |
Phase II |
Total |
|
Pig Iron |
0.66 MPTA |
- |
0.66 MTPA |
|
Coke Oven |
0.6 MPTA |
- |
0.6 MPTA |
|
Sponge Iron |
0.165 MTPA |
0.165 MPTA |
0.330 MPTA |
|
Steel |
0.8 MTPA |
0.2 MPTA |
1.00 MPTA |
|
Coal Washery at
Tubed |
2.25 MTPA |
- |
2.25 MPTA |
|
Power Plant |
35 MW |
118 MW |
153 MW |
|
| |
|
Schedules : |
|
|
|
Phase I |
|
|
| |
Capacity |
Commissioning by |
|
Pig Iron |
0.66 MPTA |
By Jun'07 |
|
Coke Oven |
0.6 MPTA |
By Dec'09 |
|
Sponge Iron |
0.165 MTPA |
By June'08 |
|
Steel |
0.8 MTPA |
By Dec'08 |
|
Coal Washery |
2.25 MTPA |
By Dec'09 |
|
Power Plant |
35 MW |
By Dec'09 |
|
| |
|
Phase II |
|
|
|
Implementation will be
starting by Nov'09 and
shall be completed by
Nov'11. |
| |
|
Upcoming Projects |
| |
|
Company Name |
Location |
Products &
Capacities |
|
Shyam Energy Ltd |
Lumshnong,
Meghalaya |
90 MW Power Plant |
|
Cement Manufacturing
Co. Ltd. |
Patratu, Jharkhand |
1 MTPA Cement Plant
500 MW Power Plant |
|
Shyam DRI Power Ltd. |
Talcher, Orissa |
1,000 MW Power Plant |
|
Shyam SEL Ltd. |
Jamuria, West Bengal |
500 MW Power Plant |
|
Cement Manufacturing
Co. Ltd. -
Project approved by
Bihar Industrial
Development Corporation |
Kahalgaon, Bihar |
1 MTPA Cement Plant
500 MW Power Plant |
|
| |